You are currently viewing CONSTRUCTION UPDATE – JUNE 2021

CONSTRUCTION UPDATE – JUNE 2021

The Following is an Excerpt from the Original Document: “Elena Construction Update”, June 8 2021

Click Here To Download The Full Document – Elena Construction Update June 2021

Elena continues to hit its milestones: 

Milestones: 

  • Render and architectural details to the façade are 60% complete with scaffolding being removed on the northern façade. Due to remove all scaffolding by early July. 
  • Permanent power with the substation now live. 
  • We are preparing install storages cages in the basement. 
  • Internal fit out of the apartments is progressing well with front doors installed to level 1 units and only minor fittings still to be installed. 
  • Initial clean has commenced. 
  • All windows and glazing have been installed. 
  • Stage 1 of the new cul-de-sac works has been completed. 
  • Commencement of sites stormwater works and preparing for civil works.

Works planned on site for the next quarter of 2021: 

  • Completion of civil works 
  • Completion of internal fit out 
  • Completion of podium landscape/pool and common areas 
  • Completion of façade works